Submittals, shop drawings, and RFIs: scope and limits of architect's review
One-line orientation
Contractors use submittals and shop drawings to show how they plan to build the work. They use a Request for Information (RFI) to ask for clarification. The architect’s review is limited.
Key points
- Submittals and shop drawings: Documents, product data, and samples prepared by the contractor or subcontractors showing how the work will be constructed. They illustrate the contractor’s plan for executing the design.
- The contractor must review and approve submittals before forwarding them to the architect (A201, Article 3 responsibility).
- The architect checks whether the submittal generally matches the contract documents and design intent. This is a limited review, not a check of every dimension, quantity, field condition, or construction method. The architect may identify a discrepancy, but the review does NOT verify the accuracy or completeness of dimensions and quantities, field measurements, fabrication processes, coordination, or construction means and methods — those remain the contractor’s responsibility.
- Common review responses: “no exceptions taken” (approved to proceed), “make corrections noted” (minor corrections, proceed with noted changes), “revise and resubmit” (not acceptable, must redo), “rejected” (does not conform).
- RFI (Request for Information): A formal written inquiry from the contractor seeking clarification or interpretation of the contract documents. Each RFI is documented on the AIA standard RFI form (AIA Document G716); the RFIs themselves are numbered and tracked in a separate log. Response is the architect’s interpretation — it does not change the contract (a change in scope still requires a CO or CCD).
- Substitution request: Separate from a submittal — the contractor proposes a product not originally specified. Requires justification and architect/owner approval. CSI Form 13.1A is commonly referenced.
Submittal, RFI, substitution: parallel paths, different purposes
Three construction-phase exchanges use the same actor columns.
View diagram Hide diagram
Scroll horizontally to explore
Architect review may identify a dimensional conflict, but it does not verify dimensional accuracy, quantities, field measurements, or coordination—or transfer that responsibility from the contractor.
Confusions / comparison
| Submittal / Shop Drawing | RFI | Substitution Request | |
|---|---|---|---|
| Purpose | Show HOW contractor will build specified elements | Request clarification/interpretation of documents | Propose an alternate product not in specs |
| Who initiates | Contractor | Contractor (or sub) | Contractor |
| Architect’s role | Limited conformance/design-concept review | Interpret contract documents; respond in writing | Evaluate and approve or reject |
| What architect does NOT verify | Dimensional accuracy, quantities, field measurements, coordination, fabrication, means & methods | N/A | N/A |
| Changes contract? | No | No (unless response triggers a CO/CCD) | Requires CO if accepted |
Related
→ pp-change-order-vs-ccd (this module): when an architect’s clarification requires a formal contract modification · pp-architect-site-observation-duties (this module): the architect’s site visit role, including rejecting nonconforming work · pp-payment-certification-g702 (this module): pay application review, another architect CA responsibility.