Contract modifications: Change Order, Construction Change Directive, and Minor Change compared
One-line orientation
Three mechanisms exist to modify an A201-based construction contract — Change Order, Construction Change Directive, and Minor Change — and they are tested because each differs in who signs, whether agreement is required, and what can change.
Key points
- Change Order (CO): A formal written amendment signed by owner + contractor + architect. Adjusts the contract sum and/or contract time. Used when all three parties agree on the scope, cost, and time impact before the work proceeds. Most common mechanism for scope changes.
- Construction Change Directive (CCD): Signed by owner + architect only. Directs the contractor to proceed with a change before owner and contractor have agreed on cost/time. Work does not wait for negotiation; adjustment is resolved later (by agreement → then CO, or by method in contract). The contractor is bound to proceed.
- Minor Change / Architect’s Supplemental Instruction (ASI): Issued by the architect alone. Must cause no change to contract sum or contract time. Used for clarifications, field corrections, and minor adjustments consistent with design intent.
Contract modifications: who signs decides which document
Who signs is the trap: a Change Order needs all three, a CCD needs owner and architect, a Minor Change / ASI is architect-only.
View diagram Hide diagram 3 panels
3 panels side by side — swipe to compare
- filled = signs (O owner · C contractor · A architect)
- open = does not sign (CCD omits the contractor; ASI is architect-only)
All three mechanisms live under A201 Article 7 — Changes in the Work.
Confusions / comparison
| Change Order (CO) | Construction Change Directive (CCD) | Minor Change / ASI | |
|---|---|---|---|
| Who signs | Owner + Contractor + Architect | Owner + Architect (contractor NOT required) | Architect alone |
| Changes contract sum? | Yes (agreed amount) | Possibly — amount resolved later | No |
| Changes contract time? | Yes (agreed extension) | Possibly — resolved later | No |
| When used | All parties agree on cost/time before proceeding | Work must proceed; cost/time not yet agreed | Clarification; no cost or time impact |
| A201 article | Article 7 | Article 7 | Article 7 |
Related
→ pp-submittals-and-rfis (this module): how the architect handles contractor-initiated information requests during CA · pp-architect-site-observation-duties (this module): architect’s authority to reject nonconforming work, which may trigger a CCD or CO · pp-payment-certification-g702 (this module): how approved Change Orders roll into the updated contract sum on pay applications.