AIA Agreementsconcept
AIA document families by delivery method: DBB, Design-Build, CM, and IPD
One-line orientation
AIA publishes different agreement sets for different delivery methods. Confirm the document edition first, then match the form numbers to the parties and delivery method.
Key points
-
Design-Bid-Build (DBB): The baseline method with separate design and construction contracts.
- Owner-Architect: B101
- Owner-Contractor: A101 (stipulated sum, after competitive bid)
- General Conditions: A201
-
Design-Build (DB): One entity (architect-led or contractor-led) holds design and construction.
- Owner-Design Builder: A141
- Architect’s services (within the design-build entity): B143
- No A201 — the design-builder assumes full responsibility under a single agreement.
-
CM as Advisor (CM-advisor): The CM is a consultant; the owner holds the construction contract directly with a general contractor.
- Owner-Architect: B132
- Owner-CM as Advisor: C132
- Owner-Contractor (GC): A132
- General Conditions: A232 (CMa Edition — incorporated by reference into A132 and B132; A201 does not apply here)
-
CM as Constructor / CM-at-risk (CMc): The CMc takes on construction risk, typically with a GMP. Engaged during design.
- Owner-Architect: B133
- Owner-CMc: A133 (cost-plus fee with GMP)
- General Conditions: A201 (referenced by A133)
-
Integrated Project Delivery (IPD): All parties collaborate from early design; shared risk and reward.
- Transitional form: one IPD-compatible set uses B195 for owner-architect, A195 for owner-contractor, and A295 for the general conditions. Other IPD forms also exist.
- Multi-party agreement: Single agreement signed by owner, architect, and contractor sharing risks and rewards.
- Single-Purpose Entity (SPE): Owner, architect, and contractor form a project-specific LLC; most integrated form.
AIA document set by delivery method
SCHEMATICEach method is a different contract topology — the AIA number just labels each edge; the general-conditions chip is the tell that flags the trap.
View diagram Hide diagram
Scroll horizontally to explore
CM-advisor general conditions are A232 (CMa Edition), not A201 — A201 travels with DBB and CMc only.
C132 (owner–CM advisor) rides alongside A132 (owner–GC), not instead of it. B143 sits inside the design-build entity, so the architect works for the builder, not the owner. A133 is itself the owner–CMc agreement (cost-plus, GMP); IPD is the transitional form; DB has none.
Confusions / comparison
| Delivery method | Owner-architect doc | Owner-contractor doc | General conditions |
|---|---|---|---|
| Design-Bid-Build (DBB) | B101 | A101 (stipulated sum) | A201 |
| Design-Build (DB) | B143 (architect in DB entity) | A141 (owner-design builder) | None (A201 not used) |
| CM as Advisor | B132 | A132 (owner-GC) + C132 (owner-CM) | A232 (CMa Edition) |
| CM as Constructor (CMc) | B133 | A133 (cost-plus/GMP) | A201 |
| IPD — Transitional | B195 | A195 | A295 |
| IPD — Multi-party / SPE | Single multi-party agreement or SPE LLC | (same) | (same) |
Related
→ AIA owner-contractor documents (this module): A101 vs A133 in depth · AIA G-series forms (this module): administrative forms used in construction under any delivery method · Delivery methods comparison (same topic): the contractual risk and schedule logic behind each method.
Spotted an issue with this card? Tell us →