Submittals, shop drawings, and RFIs: scope and limits of architect's review
One-line orientation
Contractors use submittals and shop drawings to show how they plan to build the work. They use a Request for Information (RFI) to ask for clarification. The architect’s review is limited.
Key points
Submittals and shop drawings: Documents, product data, and samples prepared by the contractor or subcontractors showing how the work will be constructed. They illustrate the contractor’s plan for executing the design.
The contractor must review and approve submittals before forwarding them to the architect (A201, Article 3 responsibility).
The architect checks whether the submittal generally matches the contract documents and design intent. This is a limited review, not a check of every dimension, quantity, field condition, or construction method. The architect may identify a discrepancy, but the review does NOT verify the accuracy or completeness of dimensions and quantities, field measurements, fabrication processes, coordination, or construction means and methods — those remain the contractor’s responsibility.
Common review responses: “no exceptions taken” (approved to proceed), “make corrections noted” (minor corrections, proceed with noted changes), “revise and resubmit” (not acceptable, must redo), “rejected” (does not conform).
RFI (Request for Information): A formal written inquiry from the contractor seeking clarification or interpretation of the contract documents. Each RFI is documented on the AIA standard RFI form (AIA Document G716); the RFIs themselves are numbered and tracked in a separate log. Response is the architect’s interpretation — it does not change the contract (a change in scope still requires a CO or CCD).
Substitution request: Separate from a submittal — the contractor proposes a product not originally specified. Requires justification and architect/owner approval. CSI Form 13.1A is commonly referenced.
Submittal, RFI, substitution: parallel paths, different purposes
Three construction-phase exchanges use the same actor columns.
View diagramHide diagram
Scroll horizontally to explore →
Architect review may identify a dimensional conflict, but it does not verify dimensional accuracy, quantities, field measurements, or coordination—or transfer that responsibility from the contractor.
Confusions / comparison
Submittal / Shop Drawing
RFI
Substitution Request
Purpose
Show HOW contractor will build specified elements
Request clarification/interpretation of documents
Propose an alternate product not in specs
Who initiates
Contractor
Contractor (or sub)
Contractor
Architect’s role
Limited conformance/design-concept review
Interpret contract documents; respond in writing
Evaluate and approve or reject
What architect does NOT verify
Dimensional accuracy, quantities, field measurements, coordination, fabrication, means & methods
N/A
N/A
Changes contract?
No
No (unless response triggers a CO/CCD)
Requires CO if accepted
Related
→ pp-change-order-vs-ccd (this module): when an architect’s clarification requires a formal contract modification · pp-architect-site-observation-duties (this module): the architect’s site visit role, including rejecting nonconforming work · pp-payment-certification-g702 (this module): pay application review, another architect CA responsibility.