Sheet G-140
PjM PACE

Project Deliveryconcept

Design-Build, Bridged Design-Build, and IPD: single- and shared-contract deliveries

One-line orientation

These methods change the usual owner-architect-contractor contract chain. Compare who contracts with the owner, when the builder joins, and how risk and reward are shared.

Key points

  • Design-Build (DB):

    • One entity (DB contractor or design-build firm) provides both design services and construction under a single owner contract.
    • Single point of responsibility — no architect/contractor finger-pointing.
    • Design-Build can shorten the schedule because design and construction may overlap. It is a tendency, not a guaranteed ranking.
    • Owner gives up independent design advocacy and some control over design decisions. The architect within the DB entity works for the contractor, not the owner.
  • Bridged Design-Build:

    • Owner retains a separate bridging architect (bridging consultant) to develop design through Schematic Design (SD) and potentially Design Development (DD).
    • Bridging architect establishes design intent, performance requirements, and criteria.
    • Owner then hands the project to a DB entity, which completes design and executes construction.
    • Gives owner more design control and quality assurance than pure DB, while still gaining single-point-of-responsibility for construction.
  • Integrated Project Delivery (IPD):

    • IPD generally brings the owner, architect, and contractor into early collaboration with shared risk and reward. A multi-party agreement is one common form, but transitional and single-purpose-entity forms also exist.
    • All three parties collaborate from early design stages; decisions are made jointly.
    • Profit is typically tied to project outcomes (schedule, budget, quality targets) — incentivizes collective performance.
    • Often useful where early collaboration and shared outcomes add value; it is not limited to one project size.

Design-Build vs bridged DB vs IPD: who contracts with whom

Three deliveries on one relationship grid — count the owner's contracts and the method names itself.

View diagram Hide diagram

Scroll horizontally to explore

Contractual relationships under Design-Build, Bridged Design-Build, and IPD, with AIA document numbers on each contract Three stacked relationship panels share one tier grid. Design-Build shows one owner contract with a design-builder that holds the architect and contractor. Bridged Design-Build shows the owner holding one agreement with a bridging architect and another with the design-builder. The IPD panel shows a common multi-party model in which owner, architect, and contractor sign one agreement and share risk, reward, and decisions. Other IPD contract forms also exist. Design-Build — one owner contractthe design-builder holds both the architect and the contractorOwnerA141B143A142C441A441ArchitectDesign-Builderone point of responsibilityContractorConsultant(s)Subcontractorsthe architect works for the design-builder, not the ownerNo general-conditions band here: with one owner agreement there is no shared rules document standing between three parties.Bridged Design-Build — two owner contractsthe owner keeps design direction by holding a bridging architect directlyOwnerB142A141B143 · A142Bridging architectdoes SD / DDDesign-Buildercompletes and builds itArchitect + Contractorboth inside the design-builderTwo owner contracts, not one — that is the whole difference from plain design-build.IPD — common multi-party model shownowner, architect, and contractor may all sign one agreementA single multi-party agreement — signed by all threeOwnerArchitectContractorIn this common model, one agreement shares risk, reward, and decisions among the team.Profit is tied to project outcomes — schedule, budget, and quality targets.

The IPD panel shows a common multi-party model, not the only possible IPD contract form. Document numbers are shown without year suffixes.

Confusions / comparison

Design-BuildBridged Design-BuildIPD
Owner contractsOne (DB entity)Two (bridging architect + DB entity)Commonly one multi-party agreement; other forms exist
Design responsibilityDB entityBridging architect (SD/DD) → DB entity (CD+)Architect within multi-party team
Single point of responsibilityYes (DB entity)Partial (DB entity for construction)Shared among all parties
Owner control of designLowModerate (protected through SD/DD)High (collaborative)
Schedule tendencyOften shorter through overlapCan preserve some overlapEarly collaboration can reduce later delays
Best forCost-driven; schedule-sensitive projectsOwner wants design intent protected before DB handoffHigh-trust teams seeking early collaboration and shared outcomes
RiskDB entity carries design + construction riskSplit: bridging architect (design intent), DB entity (execution)Shared among all parties

→ Design-Bid-Build (pp-delivery-design-bid-build): the traditional sequential baseline · CM-as-Constructor (pp-delivery-construction-manager): another early-collaboration method with a different contract structure · Cross-method comparison (pp-delivery-method-comparison): DB and IPD in the full delivery method matrix.