← Project Development & Documentation

Sheet S-103
PPDPDD CE

Concreteconcept

Precast concrete

One-line orientation

Precast concrete is plant-cast for quality and speed; prestressed precast is commonly pre-tensioned, but the pre-vs-post distinction should not be turned into an absolute rule.

Key points

  • Plant-cast for quality control: members are cast in a controlled factory environment (casting bed), giving consistent strength/finish and faster on-site erection.
  • Commonly pre-tensioned, not always: plant-cast prestressed precast members are often pre-tensioned (tendons stressed before the pour, released after cure), but precast members can also be post-tensioned and post-tensioning is not exclusive to cast-in-place work. Precast commonly uses Type III cement for high early strength to speed turnover.
  • Common members:
    • Hollow-core plank — voids reduce weight (formed by extruder, embedded tubes, or removable tubes).
    • Double-tee — efficient long-span floor/roof member.
    • Beams and columns.
    • Wall / spandrel panels.
    • Tilt-up panels — cast on the slab and tilted up via cast-in lifting rings.
  • Transport & erection limits govern member size: pieces must fit road transport and crane capacity. Typical limits are width ~12–14 ft and length ~59 ft.
  • Connections: precast is joined and tied to foundations with welded or bolted steel connectors (weld/bolt plates), grouted connections, and extended stirrups that lap into a cast-in-place topping bed for continuity.

Confusions / comparison

PrecastCast-in-place
Where castPlant / casting bedOn site, in formwork
Prestress methodCommonly pre-tensioning; post-tensioned precast also existsOften post-tensioning when prestressed
Typical cementType III (high early strength)Varies by exposure
Quality controlHigh (controlled plant)Field-dependent
Size limitTransport + craneLimited mainly by formwork/site

→ Reinforcing & prestress (this topic): pre- vs post-tensioning mechanics · Cement types & admixtures (this topic): why Type III suits precast · Slab systems (this topic): hollow-core and double-tee as floor systems.