Project Deliveryconcept
Design-Build, Bridged Design-Build, and IPD: single- and shared-contract deliveries
One-line orientation
These methods change the usual owner-architect-contractor contract chain. Compare who contracts with the owner, when the builder joins, and how risk and reward are shared.
Key points
-
Design-Build (DB):
- One entity (DB contractor or design-build firm) provides both design services and construction under a single owner contract.
- Single point of responsibility — no architect/contractor finger-pointing.
- Design-Build can shorten the schedule because design and construction may overlap. It is a tendency, not a guaranteed ranking.
- Owner gives up independent design advocacy and some control over design decisions. The architect within the DB entity works for the contractor, not the owner.
-
Bridged Design-Build:
- Owner retains a separate bridging architect (bridging consultant) to develop design through Schematic Design (SD) and potentially Design Development (DD).
- Bridging architect establishes design intent, performance requirements, and criteria.
- Owner then hands the project to a DB entity, which completes design and executes construction.
- Gives owner more design control and quality assurance than pure DB, while still gaining single-point-of-responsibility for construction.
-
Integrated Project Delivery (IPD):
- IPD generally brings the owner, architect, and contractor into early collaboration with shared risk and reward. A multi-party agreement is one common form, but transitional and single-purpose-entity forms also exist.
- All three parties collaborate from early design stages; decisions are made jointly.
- Profit is typically tied to project outcomes (schedule, budget, quality targets) — incentivizes collective performance.
- Often useful where early collaboration and shared outcomes add value; it is not limited to one project size.
Design-Build vs bridged DB vs IPD: who contracts with whom
Three deliveries on one relationship grid — count the owner's contracts and the method names itself.
View diagram Hide diagram
Scroll horizontally to explore
The IPD panel shows a common multi-party model, not the only possible IPD contract form. Document numbers are shown without year suffixes.
Confusions / comparison
| Design-Build | Bridged Design-Build | IPD | |
|---|---|---|---|
| Owner contracts | One (DB entity) | Two (bridging architect + DB entity) | Commonly one multi-party agreement; other forms exist |
| Design responsibility | DB entity | Bridging architect (SD/DD) → DB entity (CD+) | Architect within multi-party team |
| Single point of responsibility | Yes (DB entity) | Partial (DB entity for construction) | Shared among all parties |
| Owner control of design | Low | Moderate (protected through SD/DD) | High (collaborative) |
| Schedule tendency | Often shorter through overlap | Can preserve some overlap | Early collaboration can reduce later delays |
| Best for | Cost-driven; schedule-sensitive projects | Owner wants design intent protected before DB handoff | High-trust teams seeking early collaboration and shared outcomes |
| Risk | DB entity carries design + construction risk | Split: bridging architect (design intent), DB entity (execution) | Shared among all parties |
Related
→ Design-Bid-Build (pp-delivery-design-bid-build): the traditional sequential baseline · CM-as-Constructor (pp-delivery-construction-manager): another early-collaboration method with a different contract structure · Cross-method comparison (pp-delivery-method-comparison): DB and IPD in the full delivery method matrix.